ODOM Moves Into Its Next Stage of Vertical Construction
Following the completion of ODOM’s five-floor basement and 100% completion of the retail podium structure, construction is now progressing upward across both ODOM Tower and ODOM Living.
The completed retail podium forms the shared base connecting the two towers and marks another major structural stage achieved for the development. Attention is now increasingly shifting to the vertical progression of the buildings above.

ODOM Tower Progress
At ODOM Tower, overall construction progress for the zone has reached 22.8%.
Structural works from the Ground Floor through the 5th Floor are now complete, with concrete casting finished for all columns, core walls, and slabs across these levels.

This continued upward progress marks the next phase of construction as ODOM Tower begins to establish a stronger presence above the retail podium.

ODOM Living Progress
ODOM Living has also reached 22.8% overall construction progress within its zone.

Structural works from the Ground Floor through the 4th Floor are complete, including concrete casting for all columns, core walls, and slabs.

With these levels now completed, construction will continue upward as the residential tower advances through its next stages.

The latest progress marks a clear transition in ODOM’s construction journey. With the basement and retail podium structure now complete, the focus is increasingly on the vertical development of ODOM Tower and ODOM Living as both buildings continue to rise above the site.
As construction progresses, the scale and form of ODOM will become increasingly visible, bringing the development closer to its full presence on the Phnom Penh skyline.
The project team remains committed to steady progress and delivering each stage to the required quality standards as ODOM moves toward its next construction milestones.